SEQ water grid - CH2M Hill involvement ...

For those who thought CH2M Hill didn't have a look-in on the SEQ water grid:

Luggage Point AWT

Construction of the Plant will start in April 2007 and is scheduled for completion in August 2008 prior to the four month proving and commissioning period. The main activities required to construct the AWT Plant, many of which will be done in parallel using multiple work fronts, involve:

- constructing the pad foundation
- ongoing piling of the site
- constructing the AWT Plant buildings and tanks

- installing the membrane and reverse osmosis units and pumps
- laying pipelines and services trenches

- constructing roads and drains throughout the site
- installing all electrical equipment and control mechanisms
- landscaping the site grounds


Construction contractors

The construction contractors working on the site at the Luggage Point AWT Plant are CH2M Hill, Laing O’Rourke, Hatch and Connell Wagner on behalf of the WCRW Project and the Coordinator-General.

See - SEQ - WCRW Project - Luggage Point AWT.

1 Comments:

Blogger Water Hawk said...

No wonder Dr Lesley is so kean on the Beattie project for the great south east.

His research funding to the university comes from the same people who are building the plant- CH2M Hill.

This is a rerun of the Toowoomba recycle sewage experiment!

6:48 AM, February 22, 2007

 

Post a Comment

<< Home